NOTICE:
The closed rope guard of rock mucking loader machine is made and installed with two groups of waste air drill bit or 1 / 2 "steel pipe, which are fixed in the jack on the operation side, and the height is 0.3m higher than the side plate of mucking machine.
When tunnel mucking machine in the turning roadway, it is necessary to use reliable two-way auxiliary guide wheel, clean up the roadway, and send special person to command and signal contact.
Before the operation of the mucking machine, the gas safety supervisor is responsible for hanging the moraine head methane sensor on the top of the roadway 5m away from the scraper.
The fixed wedge shall be made according to the standard drawing, and shall be driven on the moraine head with relatively complete rock type as far as possible. When the fixed wedge is fixed on the coal body or clay rock, the driving depth of the fixed wedge shall be ≮ 0.8m, and that of other rock strata shall be ≮ 0.6m. Other reinforcement measures shall be adopted for the especially soft rock strata.
The rock mucking loader must be operated by operating lever.
Stable piles must be set on both sides of the tunnel mucking machine to prevent the body from sliding down. The stable piles are made of round steel with diameter of 38mm and inserted into the bedrock with a depth of ≮ 0.8m. The insertion direction is the same as the inclination of the roadway and forms an angle of 70 ~ 800 with the floor. The connection between the stabilizing pile and the tunnel mucking machine shall be made by steel wire rope with diameter not less than 15.5mm. The connection between the steel wire rope and the stabilizing pile and the scraper bucket machine shall be made by more than two pairs of rope clamps. The connection must be reliable.