NOTICE:
The movement of the bucket mucking loading machine needs to comply with the rules for the movement of the bucket rock loader in the roadway. The following is the detailed information of the second method of moving the bucket mucking machine in the roadway:
1. After firing the cannon, knock on the top first,
2. Before moving the tunnel mucking machine, clean up the gangue on the loading square and on the track, and remove the gangue on the front and back sides of the dustpan mouth (including the moving distance between the two sides of the inner roadway)
3. After confirming the safety, lift the tunnel mucking machine mouth, hang the lifting hook firmly, and lift the dustpan mouth more than 50 mm from the bottom plate
4. Loosen the front and rear rail clamps, and move a little distance back (until the rail head is exposed to facilitate the connection of the rail, use wooden wedges to pad the front and rear, nail the rail, then remove the cushion, push the mucking loading machine forward to the dustpan mouth to cover the rail The head, the rail clamp is fixed and the bucket rake machine is fixed), the steel rail is connected, and the rake bucket mucking loading machine can also be moved manually in the roadway. The moving speed should be uniform and not too fast.
5. After the bucket tunnel mucking machine moves to the predetermined position, first fix the 4 rail clamps, and lay the anchors and the rear support legs.