NOTICE:
After rock mucking loading machine firing the gun, first make a hole in the upper part of the head (or use the remaining hole), install the fixed wedge. When installing the fixed wedge, first put the end of the wire rope sleeve with the tapered sleeve into the drilled hole, and then fix it Insert and knock the wedge tightly. When disassembling, tap the end of the wedge horizontally with a hammer to loosen the wedge. Pull out the wedge first and then pull out the wire rope collar. The hole for installing the fixed wedge is preferably at an angle of 5 #176;~7 #176; to the working surface, so that the fixed wedge is not easily pulled out.
After the rock mucking loading machine fixed wedge is installed, the tail wheel can be hung on the wire rope collar. The suspension position of the tail wheel depends on the conditions of the roadway. Generally, it is better to hang above the height of 1000mm above the head rock pile. In order to reduce auxiliary labor and increase the efficiency of mechanical rock loading, the hanging position should be moved to the left and right according to the accumulation of rocks to facilitate the cleaning of the rock in the middle and on both sides.
When tunnel mucking machine suspending and removing the tail wheel, the auxiliary brake spring at the edge of the winch drum should be loosened first, so that the wire rope can be easily pulled and the tail wheel can be hung. After the tail wheel is hung, the spring can be reset or adjusted to the appropriate pressure.
After tunnel mucking machine installing the tail wheel and passing the relevant safety inspection, you can start the motor to start the rock loading operation. When working, tighten the joystick of the work roller. The work roller will pull the rake head to pick up the rock and discharge it along the trough to the discharge port. Into the mine cart, then loosen the working roller control lever, tighten the idle roller control lever to return the empty rake bucket to the head, repeat the rock-pulling action, and fill a mine cart with 2-3 consecutive picks.
The (A) rake bucket rock mucking loading machine controls the rotary valve of the pneumatic system and pushes out the heavy mining truck with a cart air cylinder. If it is used with a skip behind the inclined roadway, a middle and indirect slot can be added between the intermediate tank and the unloading tank, so as to change the position of the discharge port to make the skip full.
When the rake bucket rock mucking loading machine is used for rock loading in the inclined roadway, in addition to using the original rail clamp, a car blocking device should be added to prevent the machine from sliding down to ensure safety and reliability.
In order to ensure high productivity and easy laying of the track, the rake bucket rock loading machine should be no more than 15m away from the head. In order to avoid damage to the machine during firing, the machine is generally not less than 6m away from the head.
The movement of the shunting disc: Use the wire ropes of the winch and wind-powered winch of the rake bucket mucking machine to bypass the rope wheels hanging on the track, and fix them with bolts in the steel plate holes on the exit side of the heavy truck, and the main rope of the winch is pulled Later, it is also fixed on the steel rail. Then start and operate the wind-driven winch and rake bucket winch, the shunting disc and the rake bucket mucking machine can move backwards, and stop after the track is exposed outside the dustpan mouth. After nailing the road, use the rake winch to pull the mucking machine and shunting plate to the front position.